Platform
for Active
Information
Dissemination 
 Lehrstuhl für Angewandte Softwaretechnik  | 
| 
 | 
|||
| Date & Location | Topic | Readings | Important Dates, Deadlines | 
| Week #1: 11/02/98-11/08/98 | |||
| 11/03/98, 
 3175, 16:30  | 
Project Kickoff-Meeting | TUM Project Start | |
| 11/05/98, 
 3175, 15:00  | 
CMU Client Review | ||
| Week #2: 11/09/98-11/15/98 | |||
| 11/10/98, 
 S1128, 15:00  | 
Communication
Tutorial
 (Lotus Notes)  | 
Brügge & Dutoit 
 Project Communication  | 
|
| 11/12/98, 
 S1128, 15:00  | 
Meeting
tutorial
 First team meetings  | 
Team assignments done
 First team meeting after lecture  | 
|
| Week #3:11/16/98- 11/22/98 | |||
| 11/17/98, 
 S1128, 15:00  | 
StarNetwork
Presentation
 PAID Presentation  | 
Client visit to TUM | |
| 11/19/98, 
 S1128, 15:00  | 
CASE-Tools: Together/J | ||
| Week #4: 11/23/98-11/29/98 | |||
| 11/24/98, 
 S1128, 15:00  | 
UML | Brügge & Dutoit 
 Modeling with UML  | 
CMU Implementation Review | 
| 11/26/98, 
 S1128, 15:00  | 
Requirements Elicitation | Brügge & Dutoit 
 Requirements Elicitation  | 
|
| Week #5: 11/30/98-12/06/98 | |||
| 12/01/98, 
 S1128, 15:00  | 
Requirements Analysis | Brügge & Dutoit 
 Requirements Analysis  | 
|
| 12/03/98, 
 S1128, 15:00  | 
No lecture | dies academicus | |
| Week #6: 12/07/98-12/13/98 | |||
| 12/08/98, 
 S1128, 15:00  | 
Design Rationale 
 StarNetwork Demo  | 
Brügge & Dutoit 
 Design Rationale  | 
|
| 12/10/98, 
 3175, 15:00  | 
Client Acceptance Test | CMU Client Acceptance Test | |
| Week #7: 12/14/98-12/20/98 | |||
| 12/15/98, 
 S1128, 15:00  | 
Design Patterns I | ||
| 12/17/98, 
 S1128, 15:00  | 
Configuration Management | ||
| Week #8: 12/21/98-12/27/98 | |||
| 12/22/98, 
 S1128, 15:00  | 
Design Patterns II | ||
| 12/24/98, 
 S1128, 15:00  | 
No lecture | It's Christmas time | |
| Week #9: 01/11/99-01/17/99 | |||
| 01/12/99, 
 S1128, 15:00  | 
System Design | Brügge & Dutoit 
 System Design  | 
|
| 01/14/98, 
 S1128, 15:00  | 
System Design (continued) (no additional slides)  | 
Team RAD's first draft finished | |
| Week #10: 01/18/99-01/24/99 | |||
| 01/19/99, 
 S1128, 15:00  | 
Testing | Brügge & Dutoit 
 Integration & Testing  | 
Monday, 18th: Revised Team RAD's finished  | 
| 01/21/98, 
 S1128, 15:00  | 
Testing (continued) (no additional slides)  | 
||
| Week #11: 01/25/99-01/31/99 | |||
| 01/26/99, 
 S1128, 15:00  | 
StarNetwork Workshop | Client Visit to TUM | |
| 01/28/98, 
 S1128, 15:00  | 
no lecture | ||
| Week #12: 02/01/99-02/07/99 | |||
| 02/02/99, 
 S1128, 15:00  | 
no lecture | Monday, 1st: Team SDD's finished  | 
|
| 02/04/98, 
 S1128, 15:00  | 
Guest lecture by Raul Valdes-Perez Machine learning and discovery  | 
Friday, 5th: Coach comments about RAD and SDD are back in teams  | 
|
| Week #13: 02/08/99-02/14/99 | |||
| 02/09/99, 
 S1128, 15:00  | 
Object Design | ||
| 02/11/98, 
 S1128, 15:00  | 
Object Design (continued) (no additional slides)  | 
Deadline for RAD & SDD: Saturday, 13th | |
| Week #14: 02/15/99-02/21/99 | |||
| 02/16/99, 
 S1128, 15:00  | 
No lecture | Faschingsdienstag | |
| 02/18/98, 
 S1128, 15:00  | 
Project Management Dealer visit  | 
Brügge & Dutoit 
 Project Management  | 
|
| Week #15: 02/22/99-02/28/99 | |||
| 02/23/99, 
 S1128, 15:00  | 
PAID Review | ||
| 02/25/98, 
 S1128, 15:00  | 
Reengineering | ||
| Week #16: 03/01/99-03/07/99 | |||
| 03/02/99, 
 S1128, 15:00  | 
Client Acceptance Test Dry-Run | ODD and Prototype finished | |
| 03/04/98, 
 S1128, 15:00  | 
Client Acceptance Test | Deliverables are handed out to the client  | 
|